Well #11

WellWell1A new municipal well is being drilled to capture additional water resources. Drilling is complete to near 300 feet and will draw from the Wonewoc Aquifer. The well will provide an additional 700 gallons per minute of water during peak demands. This year the municipal system will pump near 900 million gallons of water.

Schedule:

December 2023 - Well Development

January 2024 - Well Development and pipework

February - Site work

Spring - Piping connection to Well House

Summer - Operational